Supply of Greenheart timber launch runners

Client – Saipen Srl

Contract – Supply of Greenheart timber launch runners

Timescales – 12 weeks. Timbers delivered in 10 weeks

Background – Saipen required high grade launch runners to move their latest oil installation to a transportation barge. Greenheart timber (supplied from stock) was specified due to its strength and load taking capability.

Timber Requirements – Aitken and Howard won the tender to supply the following:

  • Planed Greenheart 300mm x 400mm

Value Added – Timbers were planed to tolerance of -1/+2mm and drilled for manufacture