Fabrication and supply of Load Out timbers for wind farm project

Client – Flurocarbon

Contract – Fabrication and supply of Load Out timbers for wind farm project

Timescales – 10 weeks. Delivered as scheduled

Background – Flurocarbon was contracted to Siemens for a major wind farm project. They required high quality timbers to move a 10,000 ton control centre between transportation barges.

Timber Requirements – Aitken and Howard won the tender to supply the following:

  • 230mm x 230mm Greenheart sections

Value Added – Sections planed to -1/+1 tolerance with 4 sections bolted together to create a raft unit. A total of 16 raft units were then bolted together to create the completed launch runner.